I was at the job site (Legion) today(April 13)  and took some photos.  Basically, here's where things look to be:
  • The 120 Vac electrical and IT/Comm wiring has been installed;
  • R-12 fiberglass insulation and vapour barrier has been installed;
  • The drywall installation is in progress;
  • Windows are on-site and are beginning to be installed, starting with the smaller ones;
  • The lift has been delivered and should be installed this week.
I am waiting for an update on the HVAC system.